After the transfer of the mix to the receiving hopper of the paver from a tipper truck, it is transported through the conveyor tunnel to provide an optimal head of material in front of the paving screed. This is enabled with the aid of two separately adjustable conveyors. With the exception of the SUPER 700-3 and SUPER 800-3. These have only one conveyor.